Tersa · Energy and power generation

How Tersa migrated its waste-to-energy plant from Siemens S7 to PCS7

At Sant Adrià de Besòs, Tersa replaced a 20-year-old control system with a PCS7 DCS built for precise, redundant control. The plant was back up on time, with its teams trained on a simulator before go-live.

  • 3flue gas cleaning lines reprogrammed in PCS7 V9.0
  • 4screens per operator station instead of one

At a glance

  • Customer

    Tersa, Sant Adrià de Besòs waste-to-energy plant, Barcelona

  • Services

    Automation

  • Starting point

    A 20-year-old control system based on Siemens S7

  • Where they wanted to go

    Digital foundation: a modern, redundant DCS with more precise control and a clearer view for operators

  • Result

    PCS7 V9.0 DCS commissioned on time, three flue gas cleaning lines reprogrammed, maintenance and operations staff trained on a simulator

  • Delivered by

    AG Solution, a Quariq company

Where they were

Twenty years on the same control system

Tersa's plant at Sant Adrià de Besòs reduces the volume of Barcelona's waste by incinerating it. The energy released produces steam and electricity, and each residue is then treated according to its characteristics.

The plant's control system was 20 years old, built on Siemens S7. It still ran the process, but it no longer gave Tersa the precision of control or the speed of decision the plant needed.

Where they wanted to go

Precise, redundant control that operators can read at a glance

Tersa set three goals for the new system: more precise control of its processes, greater agility in decision-making, and guaranteed redundancy to ensure control is never interrupted.

That is the base of the factory of the future: a digital foundation on which everything else can be built. It is also where Tersa's own progression starts. A few years later, at the same plant, Tersa went on to use AI to decide when its boiler needs cleaning.

The challenge

A new control system without stretching the downtime

A migration means new hardware, new software and a new field network, installed in a working waste-to-energy plant. Tersa's first requirement for its partner was execution good enough to keep downtime to a minimum.

The second was a team that could advise on and run the project, not just install it, and that would take the initiative when something could be improved.

What we did together

New cabinets, a new network and three lines rebuilt in PCS7

We managed the project end-to-end, from initiation and planning through execution, monitoring, and closeout.

On the hardware side, we developed and installed new control cabinets, cleaned up and reorganised every field signal, migrated field communication from PROFIBUS to PROFINET, and brought the electrical drawings and documentation up to date.

On the software side, we installed the new DCS architecture and programmed the three flue gas cleaning lines in PCS7 V9.0 with the Advanced Process Library. Each operator station went from one screen to four.

Before handover, Tersa's maintenance and operations staff trained on a simulated infrastructure, so they knew the new system before they ran the plant with it.

"The project has been managed well in all its phases. We have felt very safe with the resources provided. The overall assessment in terms of management is very positive."

Alex Sas, Head of Maintenance, Tersa

Results

On time, with operators ready from the first shift

The plant was up and running on time, with all project documentation updated. Tersa now runs a DCS built for redundancy, with four screens per operator station instead of one, and a team that trained on the system before it went live.

What's next

Next at Sant Adrià: AI on the boiler

A few years later, Tersa and our team took the same plant a step further, with an AI model that decides when the boiler needs soot blowing.

What other manufacturers can take from this

Treat the migration as a first step, not a repair

Many plants, in chemicals, pharmaceuticals, and food, as well as in energy, still run on control systems that are two decades old. The case for replacing them is usually made on risk alone. Tersa made it on what it wanted next: more precise control, faster decisions and redundancy.

A migration is also the moment to clean up field signals, renew documentation and modernise the network, because the plant is open anyway. And training on a simulator before go-live is what lets operators trust the new system from the first shift.

Transformation in practice

AI

How Tersa used AI to cut soot blowing by 35%

Read the story

Automation

How a European oils and fats refiner virtualised its whole control system in four months

Read the story

View all stories