What we did together
New cabinets, a new network and three lines rebuilt in PCS7
We managed the project end-to-end, from initiation and planning through execution, monitoring, and closeout.
On the hardware side, we developed and installed new control cabinets, cleaned up and reorganised every field signal, migrated field communication from PROFIBUS to PROFINET, and brought the electrical drawings and documentation up to date.
On the software side, we installed the new DCS architecture and programmed the three flue gas cleaning lines in PCS7 V9.0 with the Advanced Process Library. Each operator station went from one screen to four.
Before handover, Tersa's maintenance and operations staff trained on a simulated infrastructure, so they knew the new system before they ran the plant with it.