Elian Barcelona · Food & Beverage

How Elian Barcelona rebuilt its plant's OT with a 10-day cutover

At its soy crush plant, Elian Barcelona moved its control system and historian onto a new virtualised, secured OT environment and added a LIMS. The switch-over fitted inside a planned 10-day shutdown, and no critical issues followed.

  • 10 dayscutover within a planned shutdown
  • < 6 monthsfrom start to go-live
  • 0critical or significant issues after go-live

At a glance

  • Customer

    Elian Barcelona, soy crush plant producing feed and food ingredients

  • Services

    OT, Automation, Cybersecurity, Data

  • Starting point

    Digital foundation: control and data systems in place, in an OT environment that needed rebuilding to support growth, security and better use of data

  • Where they wanted to go

    Digital integration: one standardised, secured OT environment where control, process and laboratory data connect

  • Result

    Project delivered in under six months, cutover within a planned 10-day shutdown, no critical or significant issues after go-live

  • Delivered by

    AG Solution, a Quariq company

Where they were

A plant growing faster than its OT environment

Elian Barcelona crushes soybeans for the feed and food industry. Demand for sustainable and speciality feed ingredients was growing, and Elian wanted to expand the range of feed ingredients its plant could process.

The systems running the plant worked. The OT environment around them was another matter: infrastructure, network, automation, data and security needed to be redesigned so they would fit together and leave room for what came next.

Where they wanted to go

One OT environment, designed as a whole

Elian wanted its OT designed as a single environment rather than system-by-system. That meant standard, secured infrastructure; a control system on a current version and modern servers; process history preserved and easy to reach; and laboratory data managed digitally and connected to the rest.

This is the groundwork of the factory of the future. Elian was consolidating its digital foundation and moving to digital integration, the stage where systems and departments share information. Everything that comes later, from data-driven decisions to AI, is built on it.

The challenge

Modernise every layer, stop production as little as possible

A soy crush plant is built to run, and every day it stands still is throughput lost. Yet the project touched almost every layer at once: network, servers, DCS, historian and lab system. All of it had to be switched over during the plant's planned shutdown, without jeopardising the restart.

So the brief had two halves that pull against each other: modernise for efficiency, security and better decisions, and keep operations as close to uninterrupted as possible.

What we did together

Six months of preparation, ten days of switch-over

Together with Elian's team, we built a structured migration plan around three priorities: precision, minimal downtime and room to scale. The project ran for under six months. The switch-over itself took ten days.

  • Infrastructure and network. We designed, built and configured a virtualised OT environment, with a dedicated OT domain and security policies aligned with industry practice.
  • Automation. The Siemens PCS7 DCS was upgraded from V9.0 to V9.1 and moved onto new VMware ESXi virtualisation servers, which makes it easier to maintain and more stable to run.
  • Data and laboratory. Historical process data and the AVEVA PI servers were migrated to the new infrastructure, preserving the history. A LabWare LIMS was implemented, bringing laboratory data into the same managed environment.
  • After go-live, our team stayed on to support the plant through its first period on the new systems.

Results

Ten days of shutdown, no critical issues

The cutover fitted inside the plant's planned 10-day shutdown, and no critical or significant issues followed go-live. Production restarted on the new systems without delays, so the modernisation cost no production time beyond a stop that was already scheduled.

Elian now runs a standardised, virtualised OT environment with its own domain and security policies, its full process history and its laboratory data under one managed architecture. The plant has the base it needs for the improvements it plans next.

What other manufacturers can take from this

The shutdown is the deadline, not the project

Many manufacturers put off modernising their OT because they cannot afford a long stop. The stop does not have to be long if the work is done before it: design, build and test the new environment alongside the running plant, and use a shutdown that is already planned to switch over. Elian needed no extra stop. The approach works for a soy crush plant, a chemicals site or a pharmaceutical facility alike.

The second lesson is to modernise the layers together. Network, servers, control system, historian, lab data and security depend on each other. Upgraded one at a time, they mean several shutdowns and interfaces that break between steps.

Transformation in practice

Automation

How a European oils and fats refiner virtualised its whole control system in four months

Read the story

Automation

How Tersa migrated its waste-to-energy plant from Siemens S7 to PCS7

Read the story

View all stories

Let's talk

Talk with our OT team

Planning a control system or infrastructure upgrade around your next shutdown? We'll help you work out what can be prepared beforehand, and how short the stop can be.