What other manufacturers can take from this
The shutdown is the deadline, not the project
Many manufacturers put off modernising their OT because they cannot afford a long stop. The stop does not have to be long if the work is done before it: design, build and test the new environment alongside the running plant, and use a shutdown that is already planned to switch over. Elian needed no extra stop. The approach works for a soy crush plant, a chemicals site or a pharmaceutical facility alike.
The second lesson is to modernise the layers together. Network, servers, control system, historian, lab data and security depend on each other. Upgraded one at a time, they mean several shutdowns and interfaces that break between steps.