Food and beverage (oils and fats)

How a European oils and fats refiner virtualised its whole control system in four months

Facing a tight deadline, the refiner upgraded its PCS7 control system and migrated the entire plant system to a VMware platform in four phases, with commissioning completed in four days.

  • 4phases
  • 4 monthsfrom start to finish
  • 4 dayscommissioning

At a glance

  • Customer

    A European oils and fats refiner

  • Services

    Automation, OT, Cybersecurity

  • Starting point

    Digital foundation: a PCS7 control system on physical servers, due for an upgrade

  • Where they wanted to go

    Digital integration: one virtualised, secured control environment, with automatic reporting and remote access for supervision and engineering

  • Result

    Whole control system upgraded and virtualised in four months, commissioning completed in four days

  • Delivered by

    AG Solution, a Quariq company

Where they were

A control system due for an upgrade, and little time to do it

Our customer refines oils and fats for a wide range of applications, through steps from neutralisation and bleaching to deodorisation and fractionation. Its plant ran on a Siemens PCS7 control system that needed upgrading, and the timeline it set for the work was tight.

Where they wanted to go

More from less hardware, and faster response

The refiner had four goals: save money, improve response times, make better use of its resources and keep downtime to a minimum. Rather than replace its servers like for like, it chose to virtualise the entire plant system, so that server capacity would be used in full and several applications could run side by side.

Its control system already gave it a sound digital foundation. The upgrade was an opportunity to move towards digital integration: one environment where supervision, reporting, and engineering connect, and where the right people can access the process remotely and securely.

The challenge

Upgrade, virtualise and secure, against the clock

Upgrading a control system and moving it onto a virtual platform is two projects in one. Opening remote access adds a third, because it changes what has to be secured.

All of it had to fit the customer's deadline, and the switch-over had to be short enough to keep downtime to a minimum.

What we did together

Four phases, four months, four days of commissioning

We planned the work in four phases, which together took four months.

We upgraded PCS7 and virtualised the entire plant system on a VMware platform, designed to ensure the servers run at full capacity with multiple applications simultaneously without affecting performance.

We also integrated security systems into the new environment to strengthen the security of both the plant and its network, and set up automatic reporting with remote access for process supervision, maintenance and engineering. Commissioning took four days.

Results

Delivered on time, with a shorter path to the process

The whole control system was upgraded and virtualised within the customer's deadline: four months from start to finish, with a four-day commissioning that kept risk and downtime low.

The refiner now runs one virtualised environment that uses its server capacity in full, with stronger plant and network security, automatic reports, and secure remote access for supervision, maintenance and engineering.

What other manufacturers can take from this

Virtualise, connect and secure in the same move

Many control system upgrades swap old servers for new ones, one-for-one. Virtualising, instead, lets a plant use the server capacity it already pays for and separates the control software from the hardware it runs on, making later upgrades easier to plan.

The same project is the right time to enable remote access for supervision and engineering, provided security is built in at the same time rather than added later. That holds in any process plant, whether it makes food, chemicals, pharmaceuticals or energy.

Transformation in practice

OT

How Elian Barcelona rebuilt its plant's OT with a 10-day cutover

Read the story

Automation

How Tersa migrated its waste-to-energy plant from Siemens S7 to PCS7

Read the story

View all stories

Let's talk

Talk with our automation team

Planning a control system upgrade? Tell us what runs on your servers today, and we'll tell you how virtualising it could change things.

Talk with our automation team